End of First Day

All the plaster has been removed in the areas that require a lateral and vertical dpc.

Works After 1
lateral and vertical dpc installed. The dpc installed is a newer type being used in the last five years, which is a gell base, which is injected into the mortar, rather drilling into bricks and pressurising and pumping in.

Works After 3
partial rendering for tanking under stairs. This is required because the garage floor is higher than the lounge floor.

Works After 4
partial rendering for tanking in the bay window. This is required because the garden is higher than the lounge floor.

A very productive first day.